| Early
in 1987, we completed the mechanical, electrical and instrumentation
design for an extension at Western Platinum for Lonmin Management
Services. This was followed by another project for the same client,
a complete platinum concentrator for Western Platinum No. 4 Shaft.
Three further plants of similar design, together with a tailings
plant, were undertaken between 1987 and 1992.
A large platinum smelter was undertaken
for Lonmin in 1990 (whilst busy with one concentrator and one tailings
plant) and brought into operation in approximately twelve months,
a proud claim by any project company we believe! In all, well over
$500m in project work has been completed for this client.
In the early 90’s a Slag Milling plant
was constructed for Western Platinum Mine, to further improve the
efficiency of this operation, which is recognized as one of the
most cost-effective producers of PGM's in the world.
After a lull period since the early 1990’s,
Lonmin once more entered an expansionary phase which called for
the doubling up of its Karee Concentrator Plant. This work was undertaken
by DRA in the year 2000/2001. This project was characterized by
an advanced level of Process Control and Automation. One of the
results of this technically advanced plant was its ability to be
brought on-stream after a very short commissioning period and ramping-up
to name plate capacity within a matter of days. Following the successful
commissioning of this project, DRA was then tasked with the responsibility
to build two larger, identical concentrators, one situated at Karee
K4 Shaft and the other one, some 30km away at Eastern Platinum.
A tight schedule was set which called for the construction within
a 15 month period. Both concentrators were tested on waste rock
in the same week, exactly on schedule and went into production three
days later.
Kroondal Platinum
Mine Project Design & Construction
A study was completed in 1999 for a Perth
based client, Aquarius Exploration, to establish a new mine at Kroondal
near Rustenburg. This led to the award of an EPCM contract, for
the design and construction of the Kroondal Platinum Mine project.
The project included a world first in the form of a production DMS
plant ahead of the UG2 Milling and Flotation section. The project
is operated on a contract basis by Minopex.
Indicative of the satisfaction of our efforts
for Aquarius Platinum, was the award in 2001 of their next project,
the Marikana Concentrator, rated at 125 000tpm, differing from Kroondal
in that it was designed without a DMS plant. This process was brought
on stream, on time and under budget.
During the construction of the Marikana project, further work was
undertaken to expand production at Kroondal from 150 000 to 200
000tpm.
Work continued for the Aquarius Group in
the form of a new concentrator termed the Kroondal PSA Project which
is a new concentrator, to access an adjacent ore-body in Anglo American’s
property at Rustenburg Platinum mine. This project was a joint venture
between Aquarius and Anglo American. Further work for Aquarius involved
the preparation of a bankable feasibility study for the Everest
South Project and the subsequent construction and operation of the
project which assisted Aquarius in achieving its target of reaching
600 000 ounces of Platinum per year. The project included surface
and underground infrastructure, and was finished on time and under
budget.
Marula Platinum Mine
Total Surface Infrastructure, Underground Conveyors
& 230,000tpm Concentrator
A milestone for DRA was the award in 2002
of our largest contract to-date, that being the Marula Project for
Impala Platinum. Our scope of work not only included the 230 000tpm
concentrator but the total surface infrastructure together with
a portion of the underground conveyors. This project represented
our first endeavour in the plus R1 Billion project league.
A further project in the “Big League”
was awarded to a joint venture company between TWP and DRA, called
Vhumbanani. This project, for Anglo Platinum, is in the R1 Billion
bracket and has been conducted on state of the art CAD equipment
using an Anglo Platinum specified 3D software design system. The
scope of Vhumbanani’s work has recently been extended to include
further work for Anglo Platinum, most notably the construction and
commissioning of the largest throughput single platinum concentrators
in the southern hemisphere, i.e. 600ktpm PP Rust plant completed
in 2007.
An earlier project completed in 2002 had
demonstrated DRA’s capability to Anglo Platinum when we installed
a 30 000tpm plant at Amandelbult, following a visit by the Anglo
Platinum team to see the plant which we had completed at Messina.
This project was extended in 2005 to 75000 TPM on the congested
brownfields site. Following the very successful completion of the
Aquarius / Anglo Platinum PSA project, Anglo Platinum awarded the
design and construction of the Mototolo 200ktpm UG2 Concentrator
to DRA. This project was again completed within budget and in record
time to meet the required performance criteria in 2006.
Messina Platinum Project
The DRA management of the Messina Platinum
Project set a significant milestone in the mining industry with
respect to the fast tracking of engineering projects. The instruction
to proceed with the design and execution of the Interim Plant Project
was received on 12 January 2001 and mechanical completion was signed
off on 25 June 2001. Remarkably, the project was also completed
well within the project budget.
In the meantime, Messina had proceeded with
the construction of the 90 000tpm Voorspoed Project. Once again
DRA collected a bonus for completion under budget and ahead of schedule.
During 2003, DRA undertook a feasibility study for Anglovaal for
its new Platinum project at Two Rivers. This project rolled into
detailed design and construction during 2005. Included in DRA’s
scope is our largest involvement to date on surface and underground
infrastructure, including underground ore and men transport. Surface
work includes our first water dam, plus roads and slimes disposal
sites.
DRA has been intimately involved in the
smelter expansion at WPL, in close conjunction with Hatch who have
supplied the actual furnace, Many other less noteworthy, but nonetheless
important, projects have been undertaken for Lonmin including compressor
upgrades, winder installations, reticulation projects etc.
Mimosa Project - Zimbabwe
Our position as the world's most experienced
contractor for PGM plant was recognized by Zimasco who selected
DRA as their consultant for the development of their Mimosa pilot
project in Zimbabwe. Following the successful operation of this
pilot project rate at 800tpd, DRA was commissioned to construct
a full scale production unit rated at 4 000tpd. This gave DRA first
hand experience in the construction of a significant project in
Zimbabwe. The depressed state of the Zimbabwean economy necessitated
innovative solutions to be found during the execution of this project.
Nevertheless, DRA completed the project on schedule and under budget.
Further expansion work was completed at
the Mimosa operation (now under the control of Aquarius Platinum
Limited) which has clearly demonstrated the viability of PGM production
on the Great Dyke of Zimbabwe. Our relationship with this client
has been almost continuous for nearly ten years.
In recognition of the experience gained
in the successful implementation of our work at Mimosa, combined
with satisfaction on the part of Impala Platinum during our construction
of the Marula Project, DRA has been awarded the engineering phase
of Zimplats’ (Impala) major project which is the Ngezi Project,
South of Harare. Extensive infrastructure work including housing,
roads, HV power systems and dams have all been part of this expansion.
The first phase plant is currently under construction.
Northam Platinum upgrade project was a 75000
ton per annum UG2 concentrator incorporating the largest rod mill
installed in Africa. Construction was completed in nine and a half
months and three and a half weeks ahead of schedule. In addition,
the project was under budget.
|